SMP Update to be Completed by Planning Commission March 2012
The previously adopted schedule has been modified and the Planning Commission will continue their review of the SMP Update through December 2011. City Council will begin their review in 2012.
Public Comment
Public comment may be provided in writing to the Planning Commission and City Council at any time during the review process. To ensure that comments are received by both reviewing bodies and entered into the official record, comments should be addressed to both the Planning Commission and City Council and sent to the City’s Department of Planning and Community Development.
pcd@bainbridgewa.gov
Modified Shoreline Master Program Update Review Schedule
|
Public Meetings
|
Shoreline Master Program Sections
Joint Meetings with PC/CC Community Open House with Staff
PC (Planning Commission) Meetings
CC (City Council) Meetings |
|
July 21 - Citizen Committees/ Staff |
Community Open House after Committees’ recommendation - Staff |
|
SS # 1 Joint PC/CC
July 21 Thurs-3 hrs. |
Overview- WAC Guideline Principles & Requirements [NNL, including Mitigation & Restoration, Use of Science; Inventory & Characterization; Public Access; Use Restrictions (e.g. armoring restrictions)] |
|
PC |
CC |
|
|
SS #2
July 28
Thurs- 3 hrs. |
SS #2
Aug 3
Wed -1 hr. |
Archaeology and Historic Resources; Agriculture; Commercial Development; Industry; Transportation; Parking; Signs; Utilities |
|
SS #3 Joint
Aug 4 Thurs-3 hrs. |
Shoreline Designations – Criteria, Mapping & Management Policies |
|
SS #4
Aug 11
Thurs- 3 hrs. |
SS #4
Aug 16
Tues- 3 hrs. |
Vegetation Conservation and Management Zone(NVZ and Clearing and Grading); Residential Development |
|
SS # 5
Aug 18
Thurs-3 hrs. |
SS #5
Aug 31 Wed-3 hrs. |
Public Access; Recreational Development; Statewide Significance; Restoration and Beach Enhancement; Forest Practices; Mining; Administration |
|
SS #6
Sept 8
Thurs-3 hrs. |
SS #6
Sept 13
Cancelled
|
Vegetation Management
Critical Areas (Environmentally Sensitive Areas); Water Quality; Flood and Stormwater |
|
SS #7
Sept 15
Thurs-3 hrs. |
SS # 7
Sept 21
Cancelled
|
Shoreline Designations;Vegetation Management
Dredging and Disposal; Landfill |
|
SS #8
Sept 22
Thurs-3 hrs.
|
SS #8
Sept 27
Cancelled
|
Overwater Structures; Boating Facilities; Aquaculture |
|
SS#9
Oct 6 Thurs-3 hrs. |
Shoreline Modification & Stabilization (Armoring); Administration |
|
SS#10
Oct 13 Thurs-3 hrs. |
Nonconforming and Commission Specific Shoreline Issue Discussion: Nonconforming Development |
|
SS#11
Oct 20
Thurs-2 hrs |
Commission Specific Shoreline Issues Discussion: Shoreline Stabilization and Nonconforming |
|
SS #12
Nov 3
Thurs-3 hrs. |
Commission Specific Shoreline Issues Discussions and Priority Aquatic designations |
|
SS #13
Nov 17
Thurs-3 hrs |
Carry-over: Priority Aquatic Designation, Shoreline Stablization
Commission Specific Shoreline Issues |
|
SS #14
Dec 8 |
Commission Specific Shoreline Issues Discussions - Carry-over items (Overwater Structures, Parking, Parks); Nonconforming development; Vegetation Conservation |
|
SS #15
Jan. 12, 2012 |
Point Monroe Designation |
| Jan. 19, 2012 |
Canceled |
|
|
Point Monroe Designation |
| Feb. 2, 2012 |
Vegetation management, environmental impacts, and nonconforming development |
| Feb. 23, 2012 |
Single-family residence mitigation |
| March 29, 2012 |
Cumulative Impact Analysis and Public Hearing |
| April 12 & 19, 2012 |
Recommendation |
|
May 22, 2012 |
First Reading-Overview of changes recommended by Planning Commission |
|
Council Meetings
To Be Determined |
Topic: Vegetation Conservation and Management Zone;
Residential Development |
|
Topic: Shoreline Modification & Stabilization (Armoring);
Nonconforming |
|
Cumulative Impact Analysis & Restoration Plan |
|
2nd Reading/Public Hearing Consider previous public hearing comment Adoption |